The Dolphin School’s New Building Update

The new build works at the Dolphin School are progressing on schedule.

Work on site in the last four weeks has focused on the weather tightness of the structure to enable the internal fit out works to advance down through the building. The majority of the purple external weather board has now been fixed back to the main frame. This purple board forms the inner layer of the wall to which the final brick or render cladding will be attached.

Internal partitions have commenced on the second floor (see picture below) and these walls will receive a plastered finish in the coming weeks.