The Dolphin School Build Update

Nearly twelve months from taking possession of the site of the former Engineering Works (Fowlers), these impressive aerial shots of the Dolphin School show how the new building has been constructed tight to all existing boundaries, which has always been one of the projects key challenges.

Dol1

 

Photos below show progress in the past two weeks with solar panels installed on the highest roof and paving slabs being laid in the science garden.

Dol2

Dol3

Internally, wiring is now being pulled through containment and conduit, whilst plasterers are busy skimming the classroom walls.